Data center construction is accelerating across North America. The logistics supporting that construction has to keep pace.
CBRE reported 7,481 MW of data center capacity under construction across eight primary North American markets during the first half of 2026, an increase of 24.8 percent year over year. More than 80 percent of that capacity was already pre-leased. At the same time, power constraints and infrastructure delivery timelines continue to affect when projects can come online.
The equipment supply chain adds another constraint. JLL reports that U.S. data center equipment lead times average 42 weeks, 83 percent above 2019 levels. Developers are preordering some materials as much as 24 months ahead of installation and holding strategic inventory for critical components.
That creates a practical logistics question: Where does equipment go between procurement and installation?
For developers, manufacturers, suppliers, and contractors, the answer requires more than finding available warehouse space. Equipment must be received, identified, stored, staged, transported, and delivered in a sequence that supports the construction schedule.
Ordering critical equipment early can protect procurement schedules, but it also moves inventory risk upstream.
Transformers, generators, switchgear, cooling equipment, electrical infrastructure, and other components may arrive well before the job site is ready for installation.
Without a structured staging strategy, project teams can face:
Equipment arriving before adequate storage is available
Limited visibility into material status and location
Additional handling as inventory is repositioned
Congestion at construction sites
Deliveries that do not match installation sequences
Difficulty responding when project schedules change
A project-based warehouse can serve as a controlled point between suppliers and the construction site.
The objective is straightforward: maintain visibility and control until each component is required.
For project logistics, square footage is only one variable.
The warehouse has to support the volume, dimensions, handling requirements, arrival patterns, and release schedule of the equipment moving through it.
A useful capacity plan should account for:
How many trucks or containers are expected each day or week?
Receiving capacity has to match those peaks without creating yard congestion or delaying unloading.
What equipment will be stored, and how can it safely be positioned?
Large electrical, cooling, and infrastructure components may require different storage configurations and material-handling processes than standard palletized inventory.
Project teams need to know what has arrived, where it is stored, its current status, and when it is scheduled to leave.
A warehouse management system can provide structured inventory control across those movements.
Materials should be positioned according to project requirements rather than simply placed wherever space is available.
Staging equipment around upcoming installation needs can reduce unnecessary movement and simplify outbound execution.
Construction sites rarely need every component simultaneously.
Coordinating releases with project milestones allows the warehouse to function as a buffer between procurement schedules and site schedules.
Transportation planning becomes especially important during the final movement from staging location to job site.
A delivery that is technically on time can still create problems if the site is not prepared to receive it.
Project teams should coordinate:
Delivery windows
Site access requirements
Equipment dimensions and weight
Unloading requirements
Installation sequence
Laydown space
Contractor availability
Changes to construction milestones
This coordination becomes increasingly important as projects scale.
Data center developers are already dealing with long equipment lead times and construction delays. JLL reported that 57 percent of data center projects experienced construction delays of three months or more in 2025.
Logistics should be structured to absorb schedule changes rather than compound them.
Visibility becomes especially valuable when equipment is procured months ahead of use.
A project team should be able to answer basic operational questions without relying on spreadsheets, emails, or manual warehouse checks:
Has the equipment arrived?
Where is it stored?
Has it been inspected?
Is it ready for release?
When is transportation scheduled?
Which project or installation phase is it assigned to?
Structured inventory management gives procurement, logistics, and project teams a common view of material status.
That becomes increasingly important when a project involves multiple suppliers, warehouses, contractors, and delivery destinations.
thyssenkrupp Supply Chain Services supports data center developers, infrastructure manufacturers, suppliers, and project teams with warehousing, transportation, inventory management, staging, value-added services, and site delivery coordination.
Our network currently includes more than 100 company-staffed and operated locations and more than 21 million square feet of warehousing capacity across North America.
That footprint gives project teams options for positioning inventory closer to manufacturing points, regional construction markets, or final project destinations.
Capabilities include:
Flexible project-based warehousing
Inventory management and visibility
Transportation and distribution
Material staging
Inspection, sorting, labeling, rework, and kitting
Site delivery coordination
Scalable support for changing project requirements
The operating model can expand or contract as a project moves through procurement, construction, installation, and commissioning phases.
Data center equipment procurement is increasingly happening months or years ahead of installation. Logistics planning should begin on a similar timeline.
Early decisions about storage locations, inventory controls, transportation, staging, and site delivery can give project teams more control when schedules change.
The warehouse then becomes more than temporary storage. It becomes part of the execution plan.
thyssenkrupp Supply Chain Services can help develop a logistics model aligned with your equipment pipeline, construction schedule, and delivery requirements.